Submittal register
Plan required submittals by specification section before work starts.
Download an Excel submittal register for preconstruction planning and procurement coordination.
What this resource is for
A submittal register is the planned inventory of required packages. It starts from the specifications and schedule; it is not the same as a live submittal log.
Specification section and requirement
Planned package title and type
Responsible subcontractor
Lead time and procurement milestone
Required-on-site date
Planned submission and review dates
How to use it
- 01
Review each relevant specification section and list every required product data, shop drawing, sample, and certificate.
- 02
Work backward from procurement and installation milestones to set required approval dates.
- 03
Promote each planned item into the active log when its package is assembled and routed.
Working from a returned PDF?
Use the AI review tool to turn reviewer comments into draft actions and a response matrix.